Creating a Value Set

A value set writes preconfigured values to a group of tags when a client writes a single identifier to the value set tag. Learn more

The procedure below creates an example value set named Production that switches three setpoint tags between low, medium, and high values. For more details on the settings, see Value Set Settings.

To create a value set:

  1. Open Workbench. In Project Explorer, expand your project > Platform Services > Unified Data Manager, right-click Value Sets and select Add Value Set. The value set form opens.

  2. In Name, enter Production.

  3. On the Value Set Tags tab, select Click here to add new item, and then enter an Alias and a Tag Name for the tag. Repeat for each tag, using the aliases Load, Pressure, and Temperature.

  4. On the Value Set Values tab, select Click here to add new item. A row is added with one column for each tag.

  5. In the new row, enter 33 in Value and Low in Name, and then enter the value to write to each tag.

    To write the current value of another tag instead of a fixed value, click in the cell, and in the Value Properties dialog, set Mode to Tag.

  6. Repeat steps 4 and 5 to add the rows 66 (Medium) and 99 (High). When finished, click Apply to save the value set.

  7. To use the value set, connect a GraphWorX process point or state field to the tag valuesets:Production and allow data entry. In runtime, enter 33, 66, or 99 to write that row's values to the three tags.